LAKE RIVER CORPORATION, Plaintiff-Appellee-Cross-Appellant, v.
CARBORUNDUM COMPANY, Defendant-Appellant-Cross-Appellee
Nos. 84-1623, 84-1688
UNITED STATES COURT OF APPEALS FOR THE SEVENTH CIRCUIT
769 F.2d 1284; 1985 U.S. App. LEXIS 21908
April 22, 1985, Argued
August 9, 1985, Decided
PRIOR HISTORY:
Appeal from the United States District Court for the Northern District of Illinois,
Eastern Division, No. 82 C 6292-Thomas R. McMillen, Judge.
DISPOSITION: AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.
OPINION: POSNER, Circuit Judge.
This diversity suit between Lake River Corporation and Carborundum Company requires us to
consider questions of Illinois commercial law, and in particular to explore the fuzzy line
between penalty clauses and liquidated-damages clauses.
Carborundum manufactures "Ferro Carbo," an abrasive powder used in making steel.
To serve its midwestern customers better, Carborundum made a contract with Lake River by
which the latter agreed to provide distribution services in its warehouse in Illinois.
Lake River would receive Ferro Carbo in bulk from Carborundum, "bag" it, and
ship the bagged product to Carborundum's customers. The Ferro Carbo would remain
Carborundum's property until delivered to the customers.
Carborundum insisted that Lake River install a new bagging system to handle the contract.
In order to be sure of being able to recover the cost of the new system ($89,000) and make
a profit of 20 percent of the contract price, Lake River insisted on the following
minimum-quantity guarantee:
In consideration of the special equipment [i.e., the new bagging system] to be acquired and furnished by LAKE-RIVER for handling the product, CARBORUNDUM shall, during the initial three-year term of this Agreement, ship to LAKE-RIVER for bagging a minimum quantity of [22,500 tons]. If, at the end of the three-year term, this minimum quantity shall not have been shipped, LAKE-RIVER shall invoice CARBORUNDUM at the then prevailing rates for the difference between the quantity bagged and the minimum guaranteed.
If Carborundum had shipped the full minimum quantity that it guaranteed, it would have
owed Lake River roughly $533,000 under the contract.
After the contract was signed in 1979, the demand for domestic steel, and with it the
demand for Ferro Carbo, plummeted, and Carborundum failed to ship the guaranteed
amount. When the contract expired late in 1982, Carborundum had shipped only 12,000 of the
22,500 tons it had guaranteed. Lake River had bagged the 12,000 tons and had billed
Carborundum for this bagging, and Carborundum had paid, but by virtue of the formula in
the minimum-guarantee clause Carborundum still owed Lake River $241,000 -- the contract
price of $533,000 if the full amount of Ferro Carbo had been shipped, minus what
Carborundum had paid for the bagging of the quantity it had shipped.
When Lake River demanded payment of this amount, Carborundum refused, on the ground that
the formula imposed a penalty. At the time, Lake River had in its warehouse 500 tons of
bagged Ferro Carbo, having a market value of $269,000, which it refused to release unless
Carborundum paid the $241,000 due under the formula. Lake River did offer to sell the
bagged product and place the proceeds in escrow until its dispute with Carborundum over
the enforceability of the formula was resolved, but Carborundum rejected the offer and
trucked in bagged Ferro Carbo from the East to serve its customers in Illinois, at an
additional cost of $31,000.
Lake River brought this suit for $241,000, which it claims as liquidated damages.
Carborundum counterclaimed for the value of the bagged Ferro Carbo when Lake River
impounded it and the additional cost of serving the customers affected by the impounding.
The theory of the counterclaim is that the impounding was a conversion, and not as Lake
River contends the assertion of a lien. The district judge, after a bench trial, gave
judgment for both parties. Carborundum ended up roughly $42,000 to the good: $269,000 +
$31,000-$24100-$17,000, the last figure representing prejudgment interest on Lake River's
damages. (We have rounded off all dollar figures to the nearest thousand.) Both parties
have appealed.
The hardest issue in the case is whether the formula in the minimum-guarantee clause
imposes a penalty for breach of contract or is merely an effort to liquidate damages. Deep
as the hostility to penalty clauses runs in the common law, see Loyd, Penalties and
Forfeitures, 29 Harv. L. Rev. 117 (1915), we still might be inclined to question, if
we thought ourselves free to do so, whether a modern court should refuse to enforce a
penalty clause where the signator is a substantial corporation, well able to avoid
improvident commitments. Penalty clauses provide an earnest of performance. The clause
here enhanced Carborundum's credibility in promising to ship the minimum amount guaranteed
by showing that it was willing to pay the full contract price even if it failed to
ship anything. On the other side it can be pointed out that by raising the cost of a
breach of contract to the contract breaker, a penalty clause increases the risk to his
other creditors; increases (what is the same thing and more, because bankruptcy imposes
"deadweight" social costs) the risk of bankruptcy; and could amplify the
business cycle by increasing the number of bankruptcies in bad times, which is when
contracts are most likely to be broken. But since little effort is made to prevent
businessmen from assuming risks, these reasons are no better than makeweights.
A better argument is that a penalty clause may discourage efficient as well as inefficient
breaches of contract. Suppose a breach would cost the promisee $12,000 in actual damages
but would yield the promisor $20,000 in additional profits. Then there would be a net
social gain from breach. After being fully compensated for his loss the promisor would be
no worse off than if the contract had been performed, while the promisor would be better
off by $8,000. But now suppose the contract contains a penalty clause under which the
promisor if he breaks his promise must pay the promisee $25,000. The promisor will be
discouraged from breaking the contract, since $25,000, the penalty, is greater than
$20,000, the profits of the breach; and a transaction that would have increased value will
be forgone.
On this view, since compensatory damages should be sufficient to deter inefficient
breaches (that is, breaches that cost the victim more than the gain to the contract
breaker), penal damages could have no effect other than to deter some efficient breaches.
But this overlooks the earlier point that the willingness to agree to a penalty clause is
a way of making the promisor and his promise credible and may therefore be essential to
inducing some value-maximizing contracts to be made. It also overlooks the more important
point that the parties (always assuming they are fully competent) will, in deciding
whether to include a penalty clause in their contract, weigh the gains against the costs
-- costs that include the possibility of discouraging an efficient breach somewhere down
the road -- and will include the clause only if the benefits exceed those costs as
well as all other costs.
On this view the refusal to enforce penalty clauses is (at best) paternalistic -- and it
seems odd that courts should display parental solicitude for large corporations. But
however this may be, we must be on guard to avoid importing our own ideas of sound public
policy into an area where our proper judicial role is more than usually deferential. The
responsibility for making innovations in the common law of Illinois rests with the courts
of Illinois, and not with the federal courts in Illinois. And like every other state,
Illinois, untroubled by academic skepticism of the wisdom of refusing to enforce penalty
clauses against sophisticated promisors, see, e.g., Goetz & Scott, Liquidated
Damages, Penalties and the Just Compensation Principle, 77 Colum. L. Rev. 554 (1977),
continues steadfastly to insist on the distinction between penalties and liquidated
damages.... To be valid under Illinois law a liquidation of damages must be a reasonable
estimate at the time of contracting of the likely damages from breach, and the need for
estimation at that time must be shown by reference to the likely difficulty of measuring
the actual damages from a breach of contract after the breach occurs. If damages would be
easy to determine then, or if the estimate greatly exceeds a reasonable upper estimate
of what the damages are likely to be, it is a penalty.
The distinction between a penalty and liquidated damages is not an easy one to draw in
practice but we are required to draw it and can give only limited weight to the district
court's determination. Whether a provision for damages is a penalty clause or a
liquidated-damages clause is a question of law rather than fact, and unlike some
courts of appeals we do not treat a determination by a federal district judge of an issue
of state law as if it were a finding of fact, and reverse only if persuaded that clear
error has occurred, though we give his determination respectful consideration.
Mindful that Illinois courts resolve doubtful cases in favor of classification as a
penalty, we conclude that the damage formula in this case is a penalty and not a
liquidation of damages, because it is designed always to assure Lake River more than its
actual damages. The formula -- full contract price minus the amount already invoiced to
Carborundum -- is invariant to the gravity of the breach. When a contract specifies a
single sum in damages for any and all breaches even though it is apparent that all are not
of the same gravity, the specification is not a reasonable effort to estimate damages; and
when in addition the fixed sum greatly exceeds the actual damages likely to be inflicted
by a minor breach, its character as a penalty becomes unmistakable. This case is within
the gravitational field of these principles even though the minimum-guarantee clause
does not fix a single sum as damages.
Suppose to begin with that the breach occurs the day after Lake River buys its new bagging
system for $89,000 and before Carborundum ships any Ferro Carbo. Carborundum would owe
Lake River $533,000. Since Lake River would have incurred at that point a total cost of
only $89,000, its net gain from the breach would be $444,000. This is more than four times
the profit of $107,000 (20 percent of the contract price of $533,000) that Lake River
expected to make from the contract if it had been performed: a huge windfall.
Next suppose (as actually happened here) that breach occurs when 55 percent of the Ferro
Carbo has been shipped. Lake River would already have received $293,000 from Carborundum.
To see what its costs then would have been (as estimated at the time of contracting),
first subtract Lake River's anticipated profit on the contract of $107,000 from the total
contract price of $533,000. The difference -- Lake River's total cost of performance -- is
$426,000. Of this, $89,000 is the cost of the new bagging system, a fixed cost. The rest
($426,000-$89,000=$337,000) presumably consists of variable costs that are roughly
proportional to the amount of Ferro Carbo bagged; there is no indication of any other
fixed costs. Assume, therefore, that if Lake River bagged 55 percent of the contractually
agreed quantity, it incurred in doing so 55 percent of its variable costs, or $185,000.
When this is added to the cost of the new bagging system, assumed for the moment to be
worthless except in connection with the contract, the total cost of performance to Lake
River is $274,000. Hence a breach that occurred after 55 percent of contractual
performance was complete would be expected to yield Lake River a modest profit of $19,000
($293,000-$274,000). But now add the "liquidated damages" of $241,000 that Lake
River claims, and the result is a total gain from the breach of $260,000, which is almost
two and a half times the profit that Lake River expected to gain if there was no breach.
And this ignores any use value or salvage value of the new bagging system, which is the
property of Lake River -- though admittedly it also ignores the time value of money; Lake
River paid $89,000 for that system before receiving any revenue from the contract.
To complete the picture, assume that the breach had not occurred till performance was
90 percent complete. Then the "liquidated damages" clause would not be so
one-sided, but it would be one-sided. Carborundum would have paid $480,000 for bagging.
Against this, Lake River would have incurred its fixed cost of $89,000 plus 90 percent of
its variable costs of $337,000, or $303,000. Its total costs would thus be $392,000, and
its net profit $88,000. But on top of this it would be entitled to "liquidated
damages" of $53,000, for a total profit of $141,000 -- more than 30 percent more than
its expected profit of $107,000 if there was no breach.
The reason for these results is that most of the costs to Lake River of performing the
contract are saved if the contract is broken, and this saving is not reflected in the
damage formula. As a result, at whatever point in the life of the contract a breach
occurs, the damage formula gives Lake River more than its lost profits from the breach --
dramatically more if the breach occurs at the beginning of the contract; tapering off at
the end, it is true. Still, over the interval between the beginning of Lake River's
performance and nearly the end, the clause could be expected to generate profits
ranging from 400 percent of the expected contract profits to 130 percent of those profits.
And this is on the assumption that the bagging system has no value apart from the
contract. If it were worth only $20,000 to Lake River, the range would be 434 percent to
150 percent....
The fact that the damage formula is invalid does not deprive Lake River of a remedy. The
parties did not contract explicitly with reference to the measure of damages if the
agreed-on damage formula was invalidated, but all this means is that the victim of the
breach is entitled to his common law damages. See, e.g., Restatement, Second, Contracts §
356, comment a (1981). In this case that would be the unpaid contract price of $241,000
minus the costs that Lake River saved by not having to complete the contract (the variable
costs on the other 45 percent of the Ferro Carbo that it never had to bag). The case must
be remanded to the district judge to fix these damages....
The judgment of the district court is affirmed in part and reversed in part, and the case
is returned to that court to redetermine both parties' damages in accordance with the
principles in this opinion. The parties may present additional evidence on remand,
and shall bear their own costs in this court.
AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.