AUTOTROL CORPORATION, Plaintiff-Appellee, v. CONTINENTAL WATER SYSTEMS
CORPORATION and OLIN CORPORATION, Defendants-Appellants
No. 90-1038
UNITED STATES COURT OF APPEALS FOR THE SEVENTH CIRCUIT
918 F.2d 689; 1990 U.S. App. LEXIS 20376
September 21, 1990, Argued
November 19, 1990, Decided
PRIOR HISTORY: Appeal from the United States District Court for the
Eastern District of Wisconsin. No. 87 C 993 -- Myron L. Gordon, Judge.
DISPOSITION: Affirmed.
OPINION: POSNER, Circuit Judge
This is a diversity suit, primarily for breach of contract. The suit was tried to a jury,
and the plaintiff, Autotrol Corporation, obtained a judgment of more than $ 1.5 million.
The appeal raises a large number of issues, only a handful of which require discussion. So
far as the remaining issues are concerned, it is enough to note that the district judge
resolved most of them in a thoroughly satisfactory manner and that the others could not
possibly have affected the outcome of the trial.
The contract provides that any dispute under it shall be resolved in accordance with the
law of Texas. Neither party questions the validity of this choice-of-law stipulation but
it is rather academic because there are no Texas cases on the hotly contested issues.
The contract, signed in May 1986, established a joint venture between Autotrol's
controls division and Continental Water Systems Corporation to create a system for water
purification based on a patented new technology, known as "electrodiarese," that
Continental owned the exclusive right to exploit. Autotrol was to manufacture the control
for the system and Continental the rest and both companies would sell the completed
systems -- Autotrol the large systems, Continental the small ones. There was an ambiguity,
later to prove critical, about the dividing line between large and small.
Before production could begin, there had to be product specifications. These had not been
completed when the contract was signed. Anticipating this possibility, the contract
provided that when approved by both parties the specifications would be attached to, and
thereby made a part of, the contract; and should the parties be "unable, in good
faith, to agree upon the contents of the Products Specifications Schedule by June 30,
1986, either party hereto may elect to terminate this Agreement." On June 25 the
parties agreed to extend this deadline to July 17. July 17 came and went and the product
specifications had not been agreed upon but neither party exercised its right of
termination. It was almost a year later, with the product specifications still not having
been agreed upon, that Continental declared the contract terminated. That is the alleged
breach. Meanwhile the other defendant, Olin Corporation, had acquired all the stock of
Continental, and according to evidence that the jury reasonably could credit had decided
that unless Autotrol acceded to the defendants' understanding of what the smallest system
was that Autotrol was entitled to sell -- which Autotrol refused to do -- Autotrol would
be encroaching on the segment of the market that Olin wanted to reserve for Continental.
The defendants argue that they were free to terminate the contract at any time after July
17, for any reason or no reason, without liability, provided only that the product
specifications had not been finally agreed upon and attached to the contract as a
schedule. Yet Continental encouraged Autotrol to continue working, which meant continue
spending, on Autotrol's share of the project for many months after July 17 -- indeed,
right up to the notice of termination -- even though the product specifications had not
been agreed upon. Autotrol does not argue that this encouragement was sufficiently
promissory in form to support liability under a theory of promissory estoppel, on which
see Restatement (Second) of Contracts § 89(c) and comment d (1981). But it does argue
that, in conjunction with Autotrol's parallel forbearance to exercise its right of
termination, Continental's encouragement supports an inference that the parties had
modified the contract to waive Continental's right to terminate after July 17 for failure
to agree on product specifications. This is assuming Continental had such a right, which
Autotrol denies, thus giving it two grounds upon which to argue that there was a breach of
contract. The jury found a breach but was not asked to indicate the ground, so we must
affirm if either ground is supportable; as a matter of fact both are.
Under either of Autotrol's theories, once July 17 came and went Continental could not
terminate the contract without liability -- ever -- even if the parties never did work out
product specifications. At first acquaintance the argument is implausible. The parties
could not go into production without such specifications. If they reached impasse after
bargaining in good faith, would not either party be entitled to walk away from the
contract without liability? Apparently not. The contract is deliberately asymmetrical with
respect to termination after July 17 (June 30 in the original contract, before the date
was extended). Until then either party can walk if the product specifications have not
been agreed upon. After that Autotrol can walk until production commences but
"Continental shall have no right to terminate this Agreement except as provided
in" certain paragraphs of the contract that relate to specific (and immaterial)
changed circumstances, such as bankruptcy, but not to failure to work out product
specifications. Not only by encouraging Autotrol to continue working after July 17, but in
the contract itself, Continental seems to have surrendered the right it would otherwise
have had to terminate the contract upon the failure of an essential condition.
What sense can this make? The answer lies in the asymmetry of the parties' position.
Continental controlled the patent on electrodiarese and if it abandoned the project, say
by failing to agree on product specifications, Autotrol would be unable to go forward and
would lose its investment. But if Autotrol abandoned the project Continental could always
get another partner. Making the contract terminable by Autotrol but not by Continental
gave Autotrol leverage to force Continental to license the patent to Autotrol on
reasonable terms if Continental lost interest in the project.
If all this is wrong and Continental somehow retained an implicit right to terminate the
contract without liability, even after July 17, provided that the parties were unable to
agree upon product specifications, still the jury was entitled to find that the parties
had modified the contract to forbid termination on this ground at least until such time as
the need to agree on product specifications was urgent and agreement impossible. That
deadline had not been reached when the defendants terminated -- on a ground, moreover,
that had nothing to do with product specifications, but rather with the division of
the market for the product. The modification was supported by consideration; both parties
benefited from relaxing the deadline, inasmuch as this allowed the project to proceed. United
States v. Stump Home Specialties Mfg., Inc., 905 F.2d 1117, 1122 (7th Cir. 1990).
Though oral, and somewhat vague about the duration of Continental's commitment, the
modification was sufficiently definite to be enforceable, cf. Goldstick v. ICM Realty,
788 F.2d 456, 462-63 (7th Cir. 1986), and an oral modification is enforceable under Texas
law even if the contract forbids oral modifications, as this one did. Adams v. Can-Dee
Oil Corp., 357 S.W.2d 808 (Tex. Civ. App. 1962). The Texas approach, by no means
idiosyncratic, 2 Farnsworth on Contracts § 7.6, at pp. 229-30 (1990), is not so frontal a
blow at freedom of contract as it may appear to be. For as Farnsworth points out, id.
at p. 230, in most of the cases in which oral modifications are enforced in the face of
prohibitory language in the contract the party seeking enforcement has relied on the
modification; and an invitation to rely, here inferable from both statements and conduct
of Continental, is the sort of waiver of a clause forbidding oral modifications that would
be honored even under the Uniform Commercial Code, which makes such clauses expressly
enforceable in contracts for the sale of goods. UCC § 2-209(2); Wisconsin Knife Works
v. National Metal Crafters, 781 F.2d 1280, 1286-88 (7th Cir. 1986).
The remaining issues relate to damages. During the year in which the contract was in
force, Autotrol incurred $ 245,000 in out-of-pocket costs of performance. There is no
quarrel over the appropriateness of awarding these costs as damages for breach of the
contract. But in addition the jury awarded Autotrol more than $ 700,000 in overhead
expenses. If, for example, a salaried engineer spent 25 percent of his time on the
project, then 25 percent of his salary and benefits during the period he was working on
the project were considered to be damages from the breach. The defendants object, pointing
out that it is merely a conjecture that if the contract had never been made in the first
place Autotrol would have replaced it with a project that would have covered the
engineer's salary and benefits.
Economists distinguish between a firm's fixed and variable costs. The former, as the name
implies, are the same whether or not the firm does anything; a good example is the fee
that a state charges for a corporate charter. The fee is paid before the firm begins
operations and is utterly invariant to the firm's fortunes. It would be an improper item
of damages for the breach of a contract because the breach could not have caused the
expense to be incurred.
Variable costs are those that vary with the firm's activity -- more precisely that are
caused by fluctuations in that activity. It is easy to see how the out-of-pocket expenses
that Autotrol incurred in the joint venture were variable costs -- specifically, variable
costs of the joint venture, that is, of the contract. Had it not been for the contract,
those expenses would not have been incurred. They are recoverable as damages because the
breach deprived Autotrol of the opportunity to recover them by making and selling the
water-purification systems envisaged by the contract.
It is more difficult to see how any part of the salary of the engineer in our illustration
is a variable cost of the contract. His salary would presumably have been paid, for a time
anyway, whether or not he worked on the electrodiarese project or, for that matter, on
some substitute project. His salary was an expense but not an expense "caused"
even in part by the project and hence, it might seem, was not a loss when the project
collapsed because of Continental's breach and Autotrol was as a consequence unable to
recoup the money that it had expended on the project.
But this analysis is superficial. Note, Home Office Overhead as Damages for
Construction Delays, 17 Ga. L. Rev. 761, 776-80 (1983). If the contract had never been
signed, the engineer would have had more time to devote to some other project of
Autotrol's. If we assume that the project would have been sufficiently profitable (which
does not mean grandly profitable) to cover the salary and benefits of Autotrol's salaried
employees who worked on it, it follows that the electrodiarese project turned this expense
into a loss by preempting the substitute project that would have enabled the expense to be
covered. Autotrol was left at the end of the day -- thanks to Continental's breach -- with
no customer to charge 25 percent of the engineer's salary and benefits to.
It is a question of fact whether, as the example assumes, salary and other overhead items
allocated as a bookkeeping matter to a broken contract would in fact have been recovered
in a substitute contract. If the victim of the breach of contract is a growing firm -- as
Autotrol was -- it is quite likely that they will be recovered. Growth implies alternative
uses for the company's workforce. If not this contract there would have been another,
and it would not have been broken -- or if it would have been broken, there would have
been the same entitlement to damages. But if the firm is declining, then it might well
have had to pay its overhead expenses out of its own pocket had this contract not been
signed, although before concluding this one would have to consider the possibility that
the firm could have economized on those expenses by layoffs and other adjustments.
It might be a useful simplification of the law of damages to have a flat rule that any
firm whose business was growing in real (i.e., inflation-adjusted) terms over the period
of the contract is entitled to recover the overhead on the contract that was broken; for
in all likelihood the firm could have substituted another contract profitable enough to
cover that overhead. But this we need not decide; and naturally we are reluctant to
speculate about the course of Texas law, let alone try to influence it. It is enough that
a reasonable jury could conclude that Autotrol probably would have recouped its overhead
expenses on other projects had the contract with Continental never been signed, instead of
wasting a year of its employees' time on this barren contract. There was testimony
that Autotrol's controls division was consistently overbooked with new projects and that
its new projects had a consistent record of profitability -- and remember that any project
that Autotrol would have substituted for the electrodiarese project, had the latter never
existed, need only have been profitable enough to cover the overhead expenses that
Autotrol would have incurred in the substitute project, using the inputs that instead it
wasted on electrodiarese, in order to justify an award of those overhead expenses to
Autotrol as damages.
Of course if this substitute project were the last of Autotrol's promising
projects, then the only thing the breach would have done was to accelerate Autotrol's
having to swallow its overhead expenses. But this is merely a variant of the
declining-firm scenario, one in which the award of overhead expenses will sometimes be
inappropriate. Sometimes, perhaps often, but not always. To repeat a previous point, a
declining firm may be able to slash its overhead expenses; and if it did not do so because
they were necessary to the performance of the contract, and now it is left holding the bag
because the contract has been broken, then those expenses are a loss caused by the breach
and are recoverable as contract damages.
The question of the proper treatment of overhead expenses arises more frequently in cases
in which the plaintiff is seeking not the expenses themselves -- they have not been
incurred -- but the price of a contract that has not yet been fully performed, and the
defendant asks that the overhead expenses assigned by the plaintiff on the uncompleted
portion of the contract be deducted, on the theory that they were saved by the breach and
therefore that their inclusion would exaggerate the plaintiff's loss. The proper analysis
of that case is symmetrical with the proper analysis of our case. Houston Chronicle
Publishing Co. v. McNair Trucklease, Inc., 519 S.W.2d 924, 932 (Tex. Civ. App. 1975); Taylor
v. Meirick, 712 F.2d 1112, 1121 (7th Cir. 1983); 3 Farnsworth on Contracts, supra,
§ 12.10, at p. 212. If the plaintiff can either cut his overhead expenses or recover them
in a substitute contract, then he indeed has not lost them as a result of the breach and
they should not be figured in his damages. But if he cannot do either of these things --
if in other words these really are fixed costs -- then the breach gives him no scope to
economize and there should be no deduction.
The breach in this case of course occurred after the overhead expenses were
incurred. This sequence meant that the breach, far from enabling those expenses to be
covered in a substitute contract, converted them from a bookkeeping entry into a loss,
because it was too late for the plaintiff to make the substitute contract that would have
enabled the plaintiff to recover the expenses. If there had been a contract price,
therefore, the jury would not have been entitled to subtract the overhead expenses from it
in figuring Autotrol's damages. The only thing to be subtracted would be expenses not yet
incurred, and therefore saved by the breach. But there was no contract price. Autotrol was
not selling something to Continental; they were joint venturers. That made figuring
profits difficult and the implicit theory of the damages award is that Autotrol would have
had zero profits on the venture, and is thus conservative. The defendants do not deny that
Autotrol would have done well enough on the contract to cover the overhead expenses
allocated to it, and with that concession Autotrol's case is complete.
The assumption of zero profits is based on the rule of Texas law "that the loss of
anticipated profits from a new business is too speculative and conjectural to support a
recovery of damages." Universal Commodities, Inc. v. Weed, 449 S.W.2d 106, 113
(Tex. Civ. App. 1969); see also Southwest Battery Corp. v. Owen, 131 Tex. 423, 427,
115 S.W.2d 1097, 1099 (1938). Were it not for that rule Autotrol would not be seeking
reliance damages, but instead expectation damages, and the issue of overhead expenses to
which we have been devoting such complex attention would be simplified. Autotrol would
have presented an estimate of the price at which it would have sold the water-purification
systems envisaged by the contract and would have subtracted the costs that it would have
incurred to complete the systems after the breach. The difference would be its damages.
Suppose that the overhead and other expenses that Autotrol incurred before the breach were
$ 1 million, the costs it would have (but had not yet) incurred to complete the systems
after the breach $ 2 million, and the price it would have obtained for the systems $ 4
million. Then its damages would be $ 2 million ($ 4 million - $ 2 million), and this
would cover the overhead expenses plus an allowance for profit. Since Autotrol was not in
fact a new business, and had an established track record on new projects from which a
projection could have been made of the likely success of the joint venture with
Continental, we are far from certain that the Texas "new business" rule should
apply to this case; but that is a matter for the Texas courts to think about; it is not an
issue for us.
The defendants place great weight on a passage in Kansas City Bridge Co. v. Kansas City
Structural Steel Co., 317 S.W.2d 370, 377 (Mo. 1958), from which we quote the gist:
"prerequisite to plaintiff's recovery of this general overhead item as part of its
damages, some evidence was essential from which the jury reasonably could have found that
such general overhead was not only an expense but also represented a loss to
plaintiff . . . Even though a percentage of that fixed overhead was properly allocable to
the Leavenworth job during the period of delay, nevertheless any amount so allocated could
not represent a loss or damage to plaintiff unless plaintiff would have, but
for the delay, obtained other work (which it did not have or which it did not in fact
obtain) sufficient in amount to have absorbed the allocated portion of general
overhead." (Italics in original.) We have no quarrel with this; it is our analysis in
a nutshell. But since the plaintiff is being asked to prove a counterfactual (what would
have happened had the contract in suit not been signed in the first place), he
should not be subjected to too demanding a burden of proof. The degree of precision that
can reasonably be demanded of a litigant, unless you want to doom his case from the
outset, depends on the nature of the issue. The most that can fairly be asked of a
plaintiff in Autotrol's shoes is to establish a reasonable probability that it would have
covered its overhead expenses by means of another contract had the contract in suit never
been made. A higher burden would not only be unrealistic but reward people who break their
contracts. A lower burden might, as noted earlier, be justified by a desire to simplify
litigation to the ultimate benefit of both plaintiffs and defendants.
The defendants argue that some of the overhead expenses that Autotrol sought to recover as
damages had been incurred either before the contract was signed, or, after the
breach, in preparation for the lawsuit; and neither sort of expense, whether overhead or
otherwise, is as a general rule recoverable as damages for a breach of contract. Cacavas
v. Zack, 43 Mich. App. 222, 227, 203 N.W.2d 913, 916 (1972) (per curiam); Hough v.
Jay-Dee Realty & Investment, Inc., 401 S.W.2d 545, 551 (Mo. App. 1966); Bazzini
v. Garrant, 116 Misc. 2d 119, 455 N.Y.S.2d 77 (Cty. Ct. 1982). The qualification,
"as a general rule," could be important, though. Texas has by statute entitled
the winning party in a contract suit to recover his reasonable attorney's fees from the
loser. Tex. Civ. Practice & Remedies Code § 38.001(8); Streeter v. Thompson,
751 S.W.2d 329, 331 (Tex. App. 1988); Gerdes v. Mustang Exploration Co., 666 S.W.2d
640, 645 (Tex. App. 1984). The statute could be thought to knock the props out from under
the rule against recovering expenses incurred in preparation for suit. But the plaintiff
does not argue this. It grants the defendants' major premise, but its witnesses testified
that all the expenses that the plaintiff sought to recover had been incurred during the
period when the contract was in effect. At the oral argument of the appeal the
plaintiff's counsel conceded with a frankness as refreshing as it is commendable that
forty hours of one of its employee's time for which the jury had awarded damages had in
fact been expended before the contract was signed. But the adjustment required by this
concession would be trivial, and as the computation of damages is in any event very far
from being an exact science we shall let the point pass. Pace Corp. v. Jackson, 155
Tex. 179, 190, 284 S.W.2d 340, 348 (1955); Restatement, supra, § 352, comment a.
In this connection we remind the reader yet again of the assumption of zero profits that
underlies the award of damages to Autotrol. Because of this assumption, the award of
damages probably on balance understates Autotrol's loss.
The final issue is the amount of Autotrol's attorney's fees. The witness who testified to
the amount of the fees was Autotrol's in-house counsel; the fees had been incurred by the
law firm hired to prosecute the lawsuit. The defendants argue that the only proper
witnesses to testify to those fees were the lawyers who billed them. Although we cannot
understand what possible ground the argument might have, it is pressed with such
force that some comment is required. It seems to us, quite to the contrary, that house
counsel is the ideal witness to testify to the amount of fees incurred. Here as in all
cases where a court awards fees, the fees must be reasonable in amount. It is hardly to be
expected that a lawyer will testify to having submitted an unreasonable bill, whereas
house counsel, who must approve the outside lawyers' bills, is in a good position to
explain to the jury the measures that he (in this case, she) took to protect the client
against exorbitant billing.
We find no reversible error in the judgment, and it is therefore
AFFIRMED.