IV. Contracts
E. Breaking contracts
2. The law regarding breach of contract
c. Liability for damages (cont'd.)
Groves (p-lessor) v John Wunder (d-lessee) 205 Minn. 163 (1939)
Illustrates an efficient breach
Posner
criticizes the size of this award. Why?
The entire gain from the breach was awarded to Groves
Makes the defendant (assuming he had anticipated the result)
indifferent between breaching and (inefficiently) performing. (F162-3)
The case raises the issue of timing in measuring damages:
Expected gain for Groves | Expected gain for John Wunder | |
$105,000 | value of sand & gravel - $105,000 - cost of grading ($60,000) |
|
+ value of grading | ||
At signing: > $60,000 |
At breach: < $12,160 |
Damages of $60K puts both parties closest to where
they expected to end up
Disadvantage per Posner: discourages efficient breach
Disadvantage of awarding $12K: frustrates and therefore discourages
making contracts
Besides: Groves has the option of renegotiating
to let John Wunder out of his contract
A pretty strong case could be made in general for
damages based on expectations at the time of the contract, in the absence of evidence that
those expectations were flawed
Avoids incentives for opportunistic behavior ex post.
A complication in this case was the Great Depression which depressed
property values--unforeseen event
Peevyhouse v. Garland Coal. 382 P. 2d 109 (1963)
Illustrates the reverse outcome of Groves v. John Wunder
The case suggests that courts will not award damages based on costs of performance if they are substantially disproportionate to the value of performance to the victim
Do courts usually base contract decisions on efficiency or intent of the parties?
Do courts usually second-guess subjective valuations?
Were any unforeseen developments discussed in this case?
What are some of the incentives that result from this case?
The case seems to open a can of worms regarding efficiency, freedom of contract, and opportunism
Groves v. John Wunder |
Peevyhouse
v. Garland Coal |
|
Type of property | Commercial | Farm |
Option: | ||
1. Cost of performance | 60K* | 29K |
2. Market value of performance | 12K | $300* |
3. Specific performance | Grade land | Restore land |
* = Case outcome |
Which option puts the parties closest
to the welfare levels they bargained for?
specific
performance has efficiency advantages
See Ulen, Thomas S. "The efficiency of specific performance:
toward a unified theory of contract remedies." Michigan Law Review 83
(1984): 341.
irony: cost allowed in Groves v. John Wunder, a commercial property but not in Peevyhouse v. Garland Coal, a residential property where aesthetics and subjective value are likely more important
Hadley v Baxendale, 9 Ex. 341 (1854) Moral hazard pulls in opposite direction of risk spreading. [this basically illustrates that liability is limited to what damages can in general be anticipated, not special damages such as lost profits, unless specifically warned of special circumstances]
Illustrates
consequential damages, which are not
traditionally awarded under the common law
"The general principle is that if a risk of loss is known
to only one party to the contract, the other party is not liable for the loss if it
occurs." (P127)
What incentive does this create during the contracting process?
Promotes disclosure of information
Example: the film from a trip
to the Himalayas
Request special handling, but then expect to pay extra for the extra
care
But note that it does result in an asymmetry:
Without specific disclosure, damages are capped by average
circumstances, but there is no floor to damages, so contract damage payments have a
downward bias.
Lake River v. Carborundum Co. 769 F.2d 1284 (1985) is a case where a contract provision was held unenforceable because the court viewed it as a penalty rather than reimbursement of actual damages. (F151) It's a Posner decision, well argued with some economic calculations.
Illustrates liquidated damages--damages actually specified in the contract as the money remedy for a breach
"Sometimes a contract will specify the damages to be awarded if there is a breach, ... and if the specification is a reasonable ex ante estimate of the likely damages from breach, it will be enforced under the rubric of liquidated damages even if the actual damages turn out to be much less (or more). But if it is plain from the beginning that the specification is designed to give the victim of the breach much more than he could expect actually to lose as a result of the breach, or the contract breaker to gain, then it is a penalty clause and is unenforceable." (P128)
"A penalty clause is a private version of a property rule." It gives promisee a right that must be bought back. A property rule may be better than a liability rule--avoids courts, expresses confidence in renegotiation options. Yet the same legal system that routinely enforces property rules created by judges and legislatures refuses to enforce property rules privately created by the people they will bind." (F151)Maxton Builders, Inc. v. Lo Galbo, 68 N.Y.2d 373, 502 N.E.2d 184 (1986) is a case upholding liquidated damages where the amount was held reasonable, since the amount (a 10% penalty for breach of a contract to purchase real estate) was close to the underlying economic loss.
If parties to contracts understand the terms that they negotiate, then the court is unlikely to raise welfare with rules that predispose against enforcing the terms.
Overall, there seems to be room for improvement in the efficiency-enhancing impact of court decisions regarding contract damages.